30th November 2010 - Snow
29th Nov 2010 - Triangle window FINALLY arrives
25th Nov 2010 - Steadily finishing off
15th Nov 2010 - Front doors
10th November 2010 - Garage door & front door
Also this week, we now have the security alarm partly commissioned, the smoke detectors fitted, the decorators putting top coat on the internal woodwork, the groundworkers almost finished the drive, the metal-work guy has measured up for the railings and gates, and the TV aerial bloke is fitting the aerial today.
The water board (Sutton & East Surrey Water) connected us on to the water main last week (cost £1580). However it is leaking at the curbside already, and has been making it rather soggy for the groundworkers finishing the drive. So Scott & Bernie have at least managed to divert the water main leak into the road gulley so it's (mostly) not coming onto our site any longer. Strictly speaking not our concern, since it's leaking on the highway side of the boundary, but it's a major pain for Scott & Bernie and not pleasant for the neighbours.
28th Oct 2010 - The gas is on
23rd Oct 2010
16th Oct 2010 - Extension roofed & scaffolding down
8th Oct 2010 - Front wall, boiler & kitchen
The front wall is 50% built - it still needs the metal work including the gates, and the Portland cap stones but is jolly nice already:
The plumber is busy putting in the boiler and the Megaflow system, and the details of the air source heat pump are being worked out too: