- paint needs touching up and finishing off in practically all the rooms
23rd Dec 2010 - Snag, snag, snaggity snag
- paint needs touching up and finishing off in practically all the rooms
18th December 2010 - We live in Fairways!
Will update the blog soon...
9th Dec 2010 - Carpets finished, Internet on
7th Dec 2010 - The neighbour's lawn
But at least the carpet was delivered ;-)
7th Dec 2010 - Underlay
The underlay for the carpet has been delivered:
... and the chippies have finished re-hanging most of the doors and rebating the double doors.
3rd December 2010 - Men at work
- 1st pass clean of the 1st floor
- final skirtings
- letter box
- wet room mirror
- window board in sun room
- this and that
1st Dec - looks pretty, but no work is happening today
30th November 2010 - Snow
29th Nov 2010 - Triangle window FINALLY arrives
25th Nov 2010 - Steadily finishing off
15th Nov 2010 - Front doors
10th November 2010 - Garage door & front door
And the massive, oak double front doors have arrived, and should be fitted soon. It partly depends on the window guys who have to fit side light windows to the front door, and the window guy is so cr*p and is not returning phone calls any longer.
Also this week, we now have the security alarm partly commissioned, the smoke detectors fitted, the decorators putting top coat on the internal woodwork, the groundworkers almost finished the drive, the metal-work guy has measured up for the railings and gates, and the TV aerial bloke is fitting the aerial today.
The water board (Sutton & East Surrey Water) connected us on to the water main last week (cost £1580). However it is leaking at the curbside already, and has been making it rather soggy for the groundworkers finishing the drive. So Scott & Bernie have at least managed to divert the water main leak into the road gulley so it's (mostly) not coming onto our site any longer. Strictly speaking not our concern, since it's leaking on the highway side of the boundary, but it's a major pain for Scott & Bernie and not pleasant for the neighbours.
28th Oct 2010 - The gas is on
23rd Oct 2010
16th Oct 2010 - Extension roofed & scaffolding down
8th Oct 2010 - Front wall, boiler & kitchen
The front wall is 50% built - it still needs the metal work including the gates, and the Portland cap stones but is jolly nice already:
The plumber is busy putting in the boiler and the Megaflow system, and the details of the air source heat pump are being worked out too:
3rd October 2010 - She is exposed
2nd October 2010 - Painting
24th Sept 2010 - Floor tiles laid & Internal doors installed
Also about 40% of the floor tiles (Saloni Hydra) have been beautifully laid too. They've done a grout sample and the Mrs has approved it. Grouting will occur on Sunday appartently - our first Sunday working of this project.
24th Sept 2010 - Apex steel at last
... and they even managed to fit them all today too. Apparently a mini-crane came and lifted everything up into place. Cool!