Well, currently it's just a question of finishing up all the loose ends. Apart from the minor matter of the triangular window in the sunroom STILL not having arrived from the cr*ppy window company, the rest is just tickling along now.
Things like:
- the painters are steadily finishing
- the Celotex insulation in the loft is now all netted in, to stop bits falling out
- the door bell is fitted
- the UFH is now working in all but one room (need to get it blown through to the study still, somehow)
- chippies have fitted the IKEA stuff in the walk-in wardrobe
- the patch panel for the internet cabling has been fitted
- the smoke alarms are now live
- the sockets are now on the wall for TV, phone & internet
- the garden fencing has been started
- the name plate for the front gates has arrived (fabulous piece of Cornish slate)
- the PIR lights for the porch & lobby are working
- the internal glass has arrived for the little windows from hall into lobby
- the labourer guy has squirted expandable foam stuff into various little holes all over the place to get things sealed up for the air test, which may be next week (if we have a triangular window by then)
- the CCTV for the drains has been done
- the various bits of drainpipe and guttering that needed to be finished off are done
- some of the bathroom mirrors have been fitted
etc. etc. etc.